Contract No: HY/2019/18

 

Wanchai Development Phase II and Central Wanchai Bypass

Sampling, Field Measurement and Testing Work (Stage 4)

 

Environmental Permit no. EP-376/2009

 

Monthly Environmental Monitoring & Audit Report

 

- SEPTEMBER 2021 -

 

CLIENTS:

PREPARED BY:

 

 

Civil Engineering and Development

Department

 

 

 

Lam Geotechnics Limited

 

 

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

Certified by:



 

 

 

 

 

                                               

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

04 October 2021


Table of contents   

EXECUTIVE SUMMARY.. 3

1           Introduction.. 5

1.1          Scope of the Report 5

1.2          Structure of the Report 5

2           PROJECT BACKGROUND.. 7

2.1          Background. 7

2.2          Scope of the Project and Site Description.. 7

2.3          Project Organization and Contact Personnel 8

3           status of regulatory compliance.. 9

3.1         Status of Environmental Licensing and Permitting under the Project 9

4           Monitoring Requirements. 10

4.1         Noise Monitoring. 10

4.2         Air Quality Monitoring. 11

5           Monitoring Results. 13

5.1         Noise Monitoring Results. 13

5.2         Air Quality Monitoring Results. 13

6           Compliance Audit.. 14

6.1         Noise Monitoring. 14

6.2         Air Quality Monitoring. 14

6.3         Review of the Reasons for and the Implications of Non-compliance. 14

6.4         Summary of action taken in the event of and follow-up on non-compliance  14

7           Cumulative Construction Impact due to the Concurrent Projects  15

8           Environmental Site Audit.. 16

9           Complaints, Notification of Summons and Prosecution.. 17

10        conclusion.. 18


lIST OF TABLES

Table 2.1      Schedule 2 Designated Projects under this Project

Table 2.2        Contact Details of Key Personnel

Table 3.1        Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Table 4.1        Noise Monitoring Stations

Table 4.2        Air Quality Monitoring Stations

Table 5.1        Noise Monitoring Stations for Contract no. HK/2012/08

Table 5.2        Air Quality Monitoring Station for Contract no. HK/2012/08

Table 9.1        Cumulative Statistics on Complaints

Table 9.2        Cumulative Statistics on Successful Prosecutions

Table 10.1      Summary of Key Construction Activities of Individual Contract(s) to be commenced in Coming Reporting Month

 

LIST OF FIGURES

Figure 2.1         Project Layout

Figure 2.2         Project Organization Chart

Figure 4.1         Locations of Environmental Monitoring Stations

 

lIST OF APPENDIces

Appendix 3.1    Environmental Mitigation Implementation Schedule

Appendix 4.1    Action and Limit Level

Appendix 6.1    Event Action Plans

Appendix 9.1    Complaint Log

EXECUTIVE SUMMARY

  1. This is the Environmental Monitoring and Audit (EM&A) Monthly Report ¡V September 2021 specific for Environmental Permit no. EP-376/2009. The EM&A report is prepared by the Environmental Team (ET) employed under Contract No. HY/2019/18 ¡V Wan Chai Development Phase II and Central Wanchai Bypass ¡V Sampling, Field Measurement and Testing Works (Stage 4). This report presents the environmental monitoring findings and information recorded during the period of 27th August 2021 to 26th September 2021. The cut-off date of reporting is at 26th of each reporting month.

 

Noise Monitoring

  1. Noise monitoring was conducted at M1a ¡V Footbridge for Ex-Harbour Road Sports Centre.
  2. With respect to the shift in major construction site portions at Wan Chai North, the noise monitoring station M1a ¡V Harbour Road Sports Centre was finely adjusted from East of Harbour Road Sports Centre to West of Harbour Road Sports Centre on 21 June 2016.
  3. With respect to the demolition of Ex-Harbour Road Sports Centre, the respective noise monitoring station M1a ¡V Harbour Road Sports Centre were finely adjusted on 16 and 25 May 2017 and thereafter to the Footbridge for Harbour Road Sports for noise monitoring.
  4. With respect to WDII RSS confirmed that the remaining works under HK/2012/08 would be tree planting works at EP-376/2009 area only, considered that no adverse noise impact would be contributed by the tree planting works, the respective noise monitoring at noise monitoring station M1a - Footbridge at EX-Wanchai Harbour Road Sports Centre was temporary suspended from 27 March 2019 onwards.

 

Air Quality Monitoring

  1. 1-hour and 24-hour Total Suspended Particulates (TSP) monitoring were conducted on every six days basis at CMA5b ¡V Pedestrian Plaza and CMA6a ¡V WDII PRE Site Office.
  2. With respect to WDII RSS confirmed that the remaining works under HK/2012/08 would be tree planting works at EP-376/2009 area only, considered that no adverse air quality impact would be contributed by the tree planting works, the respective air quality monitoring at monitoring stations CMA5b ¡V Pedestrian Plaza and CMA6a ¡V WDII PRE Site Office, were temporary suspended from 27 March 2019 onwards.

 

Complaints, Notifications of Summons and Successful Prosecutions

  1. No environmental complaint was received in this reporting month.

 

 

 

 

Site Inspections and Audit

  1. As WDII RSS confirmation of construction works completion on 1 April 2020 and agreed with IEC on 3 April 2020, the weekly environmental site inspection for Contract no. HK/2012/08 under EP-376/2009 was suspended from 3 April 2020 onward.

 

1          Introduction

1.1                Scope of the Report

1.1.1.         Lam Geotechnics Limited (LGL) has been appointed take up the role as the Environmental Team (ET) under Environmental Permit no. EP-376/2009 to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Wan Chai Development Phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008).

1.1.2.         This report documents the finding of EM&A works for Environmental Permit (EP) no. EP-376/2009 during the period of 27th August 2021 to 26th September 2021. The cut-off date of reporting is the 26th of each reporting month.

 

1.2                Structure of the Report

Section 1          Introduction ¡V details the scope and structure of the report.

 

Section 2          Project Background ¡V summarizes background and scope of the project, site description, project organization and contact details of key personnel during the reporting period.

 

Section 3          Status of Regulatory Compliance ¡V summarizes the status of valid Environmental Permits / Licenses during the reporting period.

 

Section 4          Monitoring Requirements ¡V summarizes all monitoring parameters, monitoring methodology and equipment, monitoring locations, monitoring frequency, criteria and respective event and action plan and monitoring programmes.

 

Section 5          Monitoring Results ¡V summarizes the monitoring results obtained in the reporting period.

 

Section 6          Compliance Audit ¡V summarizes the auditing of monitoring results, all exceedances environmental parameters.

 

Section 7          Cumulative Construction Impact due to the Concurrent Projects ¡V summarizes the relevant cumulative construction impact due to the concurrent activities of the concurrent Projects.

 

Section 8          Environmental Site Audit ¡V summarizes the findings of weekly site inspections undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.

 

Section 9          Complaints, Notification of summons and Prosecution ¡V summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 10        Conclusion

2          PROJECT BACKGROUND

2.1                Background

2.1.1           Wan Chai Development phase II and Central-Wan Chai Bypass (hereafter called ¡§the Project¡¨) are Designated Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) has been approved on 11 December 2008.

2.2                Scope of the Project and Site Description

2.2.1.         The design and construction of Wan Chai Development Phase II and Central Wanchai Bypass involves the construction and operation of primary and district distributor roads that is shown at Figure 2.1.

2.2.2.         The key purpose of the study area encompasses the Wan Chai harbourfront area. The area starts at the boundary of Central Reclamation Phase III (CRIII) at the west and connects to the existing Hung Hing Road at the east. The scope of the project includes:

¡P          A dual 2-lane primary distributor road, Road P2, approximately 0.6km in length; and

¡P          Other new primary and district distributor roads connecting to the slip roads of the Central-Wan Chai Bypass with a total length of approximately 0.7km.

2.2.3.         The project also contains various Schedule 2 DP that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the DP under this Project. Figure 2.1 shows the locations of these Schedule 2 DP.

Table 2.1    Schedule 2 Designated Project under this Project

Item

Designated Project

EIAO Reference

DP2

Road P2 and other roads which are classified as primary/district distributor roads

Schedule 2, Part I, A.1

 

2.2.4.         The designated project work II (DP2) was awarded to China State ¡V Build King Joint Venture HK/2012/08 (Contract Title: Wan Chai Development Phase II Central ¡V Wan Chai Bypass at Wan Chai West) as part of the Project works by the Civil Engineering and Development Department (CEDD). The construction work under Contract no. HK/2012/08 was commenced on 13 May 2015.

 

2.3                Project Organization and Contact Personnel

2.3.1           Civil Engineering and Development Department and Highway Department are the overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

 

2.3.2           The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2.  Key personnel and contact particulars are summarized in Table 2.2:

Table 2.2    Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

AECOM

Engineer¡¦s Representative for WDII

Senior Resident Engineer

Mr. S.K. Lo

3519 9033

2587 1877

Ramboll Hong Kong Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. David Yeung

3465 2888

3465 2899

Lam Geotechnics Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

 

3          status of regulatory compliance

3.1          Status of Environmental Licensing and Permitting under the Project

3.1.1.     A summary of the current status on licences and/or permits on environmental protection pertinent to the Project is shown in Table 3.1.

Table 3.1  Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Permits and/or Licences

Reference No.

Issued Date

Status

Environmental Permit

EP-376/2009

13 Nov 2009

Valid

Further Environmental Permit

FEP-01/376/2009

31 Mar 2015

Surrendered

Further Environmental Permit

FEP-02/376/2009

1 Aug 2016

Surrendered

 

3.1.2.     Implementation status of the recommended mitigation measures during this reporting month is presented in Appendix 3.1.

4          Monitoring Requirements

4.1          Noise Monitoring

NOISE Monitoring Station

4.1.1.     The noise monitoring station for the Project is listed and shown in Table 4.1 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.1    Noise Monitoring Station

District

Station

Description

Wan Chai

M1a

Footbridge for Ex-Harbour Road Sports Centre

 

Noise Monitoring Parameters, Frequency and Duration

4.1.2.     The construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq (30 minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq (5 minutes) shall be employed for comparison with the Noise Control Ordinance (NCO) criteria. Supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference.

4.1.3.     Noise monitoring shall be carried out at all the designated monitoring stations. The monitoring frequency shall depend on the scale of the construction activities. The following is an initial guide on the regular monitoring frequency for each station on a weekly basis when noise generating activities are underway:

¡P          One set of measurements between 0700 and 1900 hours on normal weekdays.

 

Monitoring Equipment

4.1.4.     As referred to in the Technical Memorandum ™ issued under the NCO, sound level meters in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the noise monitoring. Immediately prior to and following each noise measurement the accuracy of the sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements may be accepted as valid only if the calibration level from before and after the noise measurement agrees to within 1.0 dB.

4.1.5.     Noise measurements shall not be made in fog, rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in m/s.

4.2          Air Quality Monitoring

Air Quality Monitoring Stations

4.2.1.     The air quality monitoring stations for the Project are listed and shown in Table 4.2 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.2    Air Quality Monitoring Stations

Station ID

Description

CMA5b

Pedestrian Plaza

CMA6a

WDII PRE Site Office

Air QUALITY Monitoring Parameters, Frequency and Duration

4.2.2.     One-hour and 24-hour TSP levels should be measured to indicate the impacts of construction dust on air quality. The 24-hour TSP levels shall be measured by following the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.

4.2.3.     All relevant data including temperature, pressure, weather conditions, elapsed-time meter reading for the start and stop of the sampler, identification and weight of the filter paper, and any other local atmospheric factors affecting or affected by site conditions, etc., shall be recorded down in detail.

4.2.4.     For regular impact monitoring, the sampling frequency of at least once in every six-days, shall be strictly observed at all the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least three times in every six-days should be undertaken when the highest dust impact occurs.

Sampling Procedure and Monitoring Equipment

4.2.5.     High volume samplers (HVSs) in compliance with the following specifications shall be used for carrying out the 1-hour and 24-hour TSP monitoring:

¡P          0.6 ¡V 1.7 m3 per minute adjustable flow range;

¡P          Equipped with a timing / control device with +/- 5 minutes accuracy for 24 hours operation;

¡P          Installed with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;

¡P          Capable of providing a minimum exposed area of 406 cm2;

¡P          Flow control accuracy: +/- 2.5% deviation over 24-hour sampling period;

¡P          Equipped with a shelter to protect the filter and sampler;

¡P          Incorporated with an electronic mass flow rate controller or other equivalent devices;

¡P          Equipped with a flow recorder for continuous monitoring;

¡P          Provided with a peaked roof inlet;

¡P          Incorporated with a manometer;

¡P          Able to hold and seal the filter paper to the sampler housing at horizontal position;

¡P          Easily changeable filter; and

¡P          Capable of operating continuously for a 24-hour period.

 

4.2.6.     Initial calibration of dust monitoring equipment shall be conducted upon installation and thereafter at bi-monthly intervals. The transfer standard shall be traceable to the internationally recognized primary standard and be calibrated annually. The concern parties such as IEC shall properly document the calibration data for future reference. All the data should be converted into standard temperature and pressure condition.

 

Laboratory Measurement / Analysis

4.2.7.     A clean laboratory with constant temperature and humidity control, and equipped with necessary measuring and conditioning instruments to handle the dust samples collected, shall be available for sample analysis, and equipment calibration and maintenance. The laboratory should be HOKLAS accredited.

4.2.8.     Filter paper of size 8¡¨ x 10¡¨ shall be labelled before sampling. It shall be a clean filter paper with no pinholes, and shall be conditioned in a humidity-controlled chamber for over 24-hours and be pre-weighed before use for the sampling.

4.2.9.     After sampling, the filter paper loaded with dust shall be kept in a clean and tightly sealed plastic bag. The filter paper shall then be returned to the laboratory for reconditioning in the humidity controlled chamber followed by accurate weighing by an electronic balance with readout down to 0.1 mg. The balance shall be regularly calibrated against a traceable standard.

4.2.10.   All the collected samples shall be kept in a good condition for 6 months before disposal.

5          Monitoring Results

5.0.1.     The environmental monitoring will be implemented based on the division of works areas of the designated project managed under the contract with FEP applied by individual contractors.  Overall layout showing work areas of various contracts, latest status of work commencement and monitoring stations is shown in Figure 2.1 and Figure 4.1.

5.0.2.     The environment monitoring schedules for reporting month and coming month are presented in Appendix 5.1.

 

5.1          Noise Monitoring Results

5.1.1       The proposed division of noise monitoring station is summarized in Table 5.1 below.

Table 5.1    Noise Monitoring Station for Contract no. HK/2012/08

Location ID

District

Description

M1a

Wan Chai

Footbridge for Ex-Harbour Road Sports Centre

5.1.2       With respect to WDII RSS confirmed that the remaining works under HK/2012/08 would be tree planting works at EP-376/2009 area only, considered that no adverse noise impact would be contributed by the tree planting works, the respective noise monitoring at noise monitoring station M1a - Footbridge at EX-Wanchai Harbour Road Sports Centre was temporary suspended from 27 March 2019 onwards.

 

5.2          Air Quality Monitoring Results

5.2.1       The proposed division of air quality monitoring stations are summarized in Table 5.2 below.

Table 5.2    Air Quality Monitoring Station for Contract no. HK/2012/08

Station

Description

CMA5b

Pedestrian Plaza

CMA6a

WDII PRE Site Office

5.2.2       With respect to WDII RSS confirmed that the remaining works under HK/2012/08 would be tree planting works at EP-376/2009 area only, considered that no adverse air quality impact would be contributed by the tree planting works, the respective air quality monitoring at air quality monitoring stations CMA5b ¡V Pedestrian Plaza and CMA6a ¡V WDII PRE Site Office  were temporary suspended from 27 March 2019 onwards

6          Compliance Audit

6.0.1.     The Event Action Plan for construction noise and air quality are presented in Appendix 6.1.

6.1          Noise Monitoring

6.1.1       With respect to WDII RSS confirmed that the remaining works under HK/2012/08 would be tree planting works at EP-376/2009 area only, considered that no adverse noise impact would be contributed by the tree planting works, the respective noise monitoring at noise monitoring station M1a - Footbridge at EX-Wanchai Harbour Road Sports Centre was temporary suspended from 27 March 2019 onwards.

 

6.2          Air Quality Monitoring

6.2.1       With respect to WDII RSS confirmed that the remaining works under HK/2012/08 would be tree planting works at EP-376/2009 area only, considered that no adverse air quality impact would likely be contributed by the tree planting works, the respective air quality monitoring at air quality monitoring stations CMA5b ¡V Pedestrian Plaza and CMA6a ¡V WDII PRE Site Office were temporary suspended from 27 March 2019 onwards.

 

6.3          Review of the Reasons for and the Implications of Non-compliance

6.3.1       As WDII RSS confirmation of construction works completion on 1 April 2020 and agreed with IEC on 3 April 2020, the weekly environmental site inspection for Contract no. HK/2012/08 under EP-376/2009 was suspended from 3 April 2020 onward.

 

6.4          Summary of action taken in the event of and follow-up on non-compliance

6.4.1       As WDII RSS confirmation of construction works completion on 1 April 2020 and agreed with IEC on 3 April 2020, the weekly environmental site inspection for Contract no. HK/2012/08 under EP-376/2009 was suspended from 3 April 2020 onward.

7                     Cumulative Construction Impact due to the Concurrent Projects

7.0.1.     According to the Condition 3.4 of the EP-376/2009, this section addresses the relevant cumulative construction impact due to the concurrent activities of the current projects including the Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) and Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel).

7.0.2.     According to the Final EM&A report of Central Reclamation Phase III (CRIII) for Contract HK 12/02, the major construction activities were completed by end of January 2014 and no construction activities were undertaken thereafter and the water quality monitoring was completed in October 2011.  As such, it is considered that there were no cumulative construction impact due to the concurrent activities of the current projects with the Central Reclamation Phase III (CRIII) undertaken by contractor HK12/02 in the reporting month.

7.0.3.     According to the construction programme of Central-Wanchai Bypass at Wanchai West at the Central Reclamation Phase III area, no construction works was conducted in September 2021 reporting period. In view of the above, the cumulative construction impact due to the Central Reclamation Phase III (CRIII) was not anticipated.

7.0.4.     According to the construction programme of Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects, no construction works under Wan Chai Development Phase II was conducted at Wan Chai. The major construction activities under Central-Wan Chai Bypass and Island Eastern Corridor Link Projects were bridge noise enclosure installation works, road works, drainage works and soft landscape works at North Point area in the reporting period. In addition, other non-Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects were observed undertaken at Wan Chai North and North Point area.

7.0.5.     As relevant site mitigation measures for air quality and construction noise were implemented, no significant air quality impact and noise impact from construction activities was concluded in the reporting period. Besides, no construction work was conducted at EP-376 area in the reporting period. Thus, it is evaluated that the cumulative construction impact from the concurrent projects including Wan Chai Development Phase II (WDII), Central- WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) was insignificant.

8          Environmental Site Audit

8.0.1.     As WDII RSS confirmation of construction works completion on 1 April 2020 and agreed with IEC on 3 April 2020, the weekly environmental site inspection for Contract no. HK/2012/08 under EP-376/2009 was suspended from 3 April 2020 onward.

9          Complaints, Notification of Summons and Prosecution

9.0.1.     No environmental complaint was received in the reporting period.

9.0.2.     The details of cumulative complaint log and updated summary of complaints are presented in Appendix 9.1

9.0.3.     Cumulative statistic on complaints and successful prosecutions are summarized in Table 9.1 and Table 9.2 respectively.

Table 9.1    Cumulative Statistics on Complaints

Reporting Period

No. of Complaints

Commencement works (May 2015) to last reporting month

0

September 2021

0

Total

0

 

Table 9.2    Cumulative Statistics on Successful Prosecutions

Environmental Parameters

Cumulative No. Brought Forward

No. of Successful Prosecutions this month (Offence Date)

Cumulative No. Project-to-Date

Air

0

0

0

Noise

0

0

0

Water

0

0

0

Waste

0

0

0

Total

0

0

0

10           conclusion

10.0.1.   The EM&A programme was carried out in accordance with the EM&A Manual requirements, minor alterations to the programme proposed were made in response to changing circumstances.